There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1
Dear Neighbour
Please see below activities relating to the COLPAI Project, which are due to take place from Monday 9 March 2020.
Monday 9 March - Friday 13 March
Highlights:
Out of hours site deliveries will take place on Monday 9 March 2020 and Wednesday 11 March. These deliveries will take place to allow for the delivery of a piling rig (9/03/20) and a crawler crane (11/03/20). These deliveries will arrive on-site at 6.00am on each day. To minimise the disturbance on our neighbours, works on offload these deliveries will not begin until 8am.
Works will include:
Saturday 14 March & Sunday 15 March
Notable Points
On-site security
Deliveries
Non-ISG Works
Working Hours
Monday to Friday 08:00 to 18:00
Saturday 9:00 to 14:00
Consented Reduced Impact Hours
During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
Monday to Friday 10:00 to 12:00 and 14:00 to 16:00
Noise, dust and vibration monitoring is in place.
For site emergencies, please contact:
Steven McCarthy, ISG
T: 07825 719 496
Stephen Beattie, ISG
T: 07816 418 156