DETAILS OF WORK | COST TO THE BLOCK | COST TO THE FLAT | |
At Current Prices | At Current Prices | ||
Podium Repairs & Water Proofing | £248,986 | £1,580 | |
External/Internal Repairs & Redecoration | £161,125 | £1,023 | |
Window Replacement | £4,271,800 | £27,112 | |
Communal Heating Installation | £2,255,018 | £14,312 | |
Roof Renewal | £429,286 | £2,725 | |
Landlords Electrical Remedial Works | £548,550 | £3,481 | |
AGGREGATE AMOUNTS OF ABOVE ESTIMATES | £7,914,765 | £50,233 | |