Latest Activity

Helen Tremaine posted an event

Barbican Library exhibition - Society of Artists in Architecture at Barbican Library, Barbican Centre.

September 2, 2022 at 9:15am to September 28, 2022 at 5:30pm
Barbican LibraryExhibition of the Society of Artist in Architecture (SocAA) – ‘Cities’All works are for sale and the Private View on Monday 5 September from 6.00 – 8.30 is open to all. Drinks and canapes will be provided. Please respond through Eventbrite ‘SocAA Barbican Library Private View’ https://www.eventbrite.co.uk/e/395090705937 or email the secretary below to register your interest and get a ticket. See More
Aug 9
Jax posted discussions
Aug 8
Christine Clifford replied to Jax's discussion I know we need Lecky but this is sad and noisy and dusty and dug up 3 time since new pavement laid a few months ago.
"At least they a dealing with it all this time instead of patching "
Aug 5
Jax posted a discussion
Aug 4

Forum

HEALTH & WELLBEING

135 discussions

ESTATE OFFICE ANNOUNCEMENTS

607 discussions

GENERAL COMMENTS & QUERIES

1353 discussions

MAJOR WORKS & PROJECTS

120 discussions

COLPAI

Site of former Richard Cloudesley School

168 discussions

BERNARD MORGAN HOUSE

16 discussions

COMMUNITY CENTRE

21 discussions

ITEMS FOR SALE OR RECYCLE

221 discussions

@GoldenLaneEC1

Text Box

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

COLPAI Project Weekly Works Update – W/C Monday 24 August 2020

Dear Neighbour
 
Please see below activities relating to the COLPAI Project, which are due to take place from Monday 24 August 2020.  
 
Monday 24 August – Friday 28 August 
ISG works will include:
  • Residential basement construction, including concrete pours throughout the week
  • Brickwork and scaffolding to school and hall externally
  • Internal fit out works to the school.
 
Please note, works are scheduled to take place on Saturday 23 August.
 
Deliveries 
Deliveries taking place throughout the week include:
 
  • Delivery of concrete to the site
  • Delivery of bricks and blocks to the site
  • Delivery of scaffold to the site
  • Delivery of screed to the site.
 
ISG On-Site Security 
 
  • Security guard on-site full time 7am – 6.30pm
  • CCTV security cameras are now monitoring the site 24 hours a day, 7 days a week.
 
The City of London Corporation also has CCTV monitoring of the site in place.
 
Working Hours 
Monday to Friday – 8am to 6pm
Saturday – 9am to 2pm
 
Consented Reduced Impact Hours 
During reduced impact hours, works will still take place on-site. However, works will not involve percussive machinery or other similar construction involving heavy machinery.
 
Monday to Friday 10am to 12pm and 2pm to 4pm
 
Noise, dust and vibration monitoring is in place. 
 
Please visit our project website www.colpai-project.co.uk/monitoring-data to view the monthly monitoring data results. Moving forward, we will upload the data on a monthly basis. The monitoring data will also be put up onto the site noticeboard.
 
We have also set up a page on our website to show progress images on-site. To view, please visit https://www.colpai-project.co.uk/progress-onsite. We will update with further images as we move forward.
 
For site emergencies, please contact:
Steven McCarthy, ISG                                                   
T: 07825 719 496