Latest Activity

Learning Through the Arts posted a discussion

Free October half term Children Activities

Join our Family art workshops inspired by Black History Month at the Golden Lane Community Centre.See More
10 hours ago
Richard posted a discussion

Free - Convector Heater

I have a convector heater that has been sitting in my cupboard for a few years and I have only used it a handful of times. It is in perfect working order and excellent condition and free for anyone that wants it.I have attached a couple of pics and this is a link to the same model, although it is no longer available to buy and my one is white, not purple.https://www.robertdyas.co.uk/connect-it-2000w-convector-heater-purpleIt is light and easy to carry but I will happily drop it off to anyone on the estate.See More
yesterday
GLE Website Comms Team posted events
yesterday
Richard replied to Patsy's discussion Which is best broadband provider?
"I have been with BT for years. It is not full fibre, I think it is fibre to cabinet. When I first moved from Cullum Welch to Great Arthur there were a few teething problems but that was over 4 years ago and I have not had any problems since. I get…"
yesterday

Forum

HEALTH & WELLBEING

140 discussions

ESTATE OFFICE ANNOUNCEMENTS

608 discussions

GENERAL COMMENTS & QUERIES

1360 discussions

MAJOR WORKS & PROJECTS

120 discussions

COLPAI

Site of former Richard Cloudesley School

168 discussions

BERNARD MORGAN HOUSE

16 discussions

COMMUNITY CENTRE

21 discussions

ITEMS FOR SALE OR RECYCLE

223 discussions

@GoldenLaneEC1

Text Box

Facebook

There are four Golden Lane Estate related facebook accounts and you can follow them here: goldenlaneEC1 

Golden Lane Estate / RCS site 

Save Bernard Morgan House

City of London

DETAILS OF WORK COST TO THE BLOCK COST TO THE FLAT
At Current Prices At Current Prices
Podium Repairs & Water Proofing

£274,178

£1,740
External/Internal Repairs & Redecoration £157,573 £1,000
Window Replacement £11,998,219 £76,147
Communal Heating Installation £2,797,594 £17,755
Roof Renewal £475,063 £3,015
Landlords Electrical Remedial Works  £606,907 £3,852
 
AGGREGATE AMOUNTS OF ABOVE ESTIMATES £16,309,534 £103,509

Views: 466

Attachments:

Reply to This

Replies to This Discussion

So does the Great Arthur House successful challenge to similar costs affect this ?

Good question. We need to find out. By any chance, do you know when is the next residents meeting?

Sorry no idea.

Is there an agreed percentage contribution from the Leaseholders? It's not so clear from the latest summary.

Another good question. We need to ask City of London about it.

Does anyone know when is the next residents meeting?

GLERA has just been able to confirm next general meeting for Monday 31 October 7 pm downstairs in the Community Centre. Notices will go up next week.

Thank you for the update!

On the meeting minutes from the Residents Liaison Group of the 25th of August there is mention of a published Simplified Cost Document but it is not attached to the published minutes. Did any of the participants get hold of it?