DETAILS OF WORK | COST TO THE BLOCK | COST TO THE FLAT | |
At Current Prices | At Current Prices | ||
Podium Repairs & Water Proofing | £284,293 |
£1,804 | |
External/Internal Repairs & Redecoration | £163,783 | £1,037 | |
Window Replacement | £14,536,000 | £92,000 | |
Communal Heating Installation | £2,907,844 | £18,404 | |
Roof Renewal | £501,191 | £3,172 | |
Landlords Electrical Remedial Works | £629,044 | £3,981 | |
AGGREGATE AMOUNTS OF ABOVE ESTIMATES | £19,022,845 | £120,398 | |
Tags:
Thanks Alex. What is the source of these numbers?
It is remarkable that we are charged for podium repairs, when the City has without anyone consent turned it into a public square and thoroughfare.
And then the rest :)
Thanks for sharing. That has gone up nearly 20k since last July. That's roughly a 20% increase in 7 months! The window replacement scheme is out of control. Doesn't bode well for the other blocks on the estate who are being deprioritised in favour of Cresent House.